Sites come online in phases.
| Phase | Sites | Cumulative | Target |
|---|---|---|---|
| Phase 1A1 | 60 sites | 60 total | Target Jan 31, 2027 |
| Phase 1A2 | 60 sites | 120 total | Target Apr 30, 2027 |
| Phase 1A3 | 74 sites | 194 total | Target Jun 30, 2027 |
| Phase 1B | 36 sites | 230 total | Target Aug 31, 2027 |
| Phase 2A | 60 sites | 290 total | Target Sep 30, 2027 |
| Phase 2B | 37 sites | 327 total | Target Jan 31, 2028 |
All 327 sites complete by January 31, 2028.
Target dates, subject to construction progress.